Abingdon Villas
Location: London W8 6BU
Client: GTM Maintenance Ltd
Project Overview:
Live plantroom replacement and upgrade completed within a restricted shutdown period for occupied residential properties.
Works Completed:
* Designed plantroom layout from schematic drawings.
* Installed 2 × Hamworthy Powerstock calorifiers.
* Installed 2 × Ideal Evomax 2 boilers.
* Completed installation within a constrained space adjacent to the existing plantroom.
* Undertook live changeover within a four-hour shutdown window.
* Removed and disposed of decommissioned plant and pipework.