Create Your First Project

Start adding your projects to your portfolio. Click on "Manage Projects" to get started

Abingdon Villas

Location: London W8 6BU
Client: GTM Maintenance Ltd

Project Overview:
Live plantroom replacement and upgrade completed within a restricted shutdown period for occupied residential properties.

Works Completed:

* Designed plantroom layout from schematic drawings.
* Installed 2 × Hamworthy Powerstock calorifiers.
* Installed 2 × Ideal Evomax 2 boilers.
* Completed installation within a constrained space adjacent to the existing plantroom.
* Undertook live changeover within a four-hour shutdown window.
* Removed and disposed of decommissioned plant and pipework.